- the loan amount needed and purpose;
- the project components and financing plan showing financier of each component;
- which agency will execute the project and its institutional strengths and weaknesses;
- recommendations on how to address potential problems (if any);
- justification for the project; and
- ability of the borrower to repay loan
Principal Appraisal Criterion
The principal appraisal methodology for disaster mitigation and rehabilitation projects will be a Least Cost Analysis approach.
Required Data Elements
Project Background and History
Macro-Economic Factors/Considerations
Sector Analysis
CDB's Contribution/Previous Lending (Sector)
Lessons Learnt
Objectives/Rationale
Location and Site
Design/Alternatives/Technology/Least Cost Analysis
Project Description/Scope
Capital Cost and Project Financing/Commitments
Implementation Plan
Procurement
Disbursement
Operation/Production/Process Description
Project Management
Project Risk
Environment and Social Impact Analysis
Loan Amount - CDB Financing
Repayment Terms
Conditions
Reports and Records
|