January
1 to June 30, 2000
Audit Reports
Six audits which were scheduled in
the Inspector General's 2000 audit plan were performed during the
period ended June 30, 2000.
Audit (SG/OIG/AUDIT-01/00) was
carried out to evaluate internal controls within the Office of
Science and Technology (OST). Selected operational procedures and
transactions were examined to verify whether OST is carrying out its
responsibilities in accordance with OAS policies and procedures. The
audit determined that for the most part, internal controls within
OST are adequate. The main weaknesses identified were (a) Monthly
leave Report balances did not agree with the summaries obtained from
the records provided by the Department of Financial Services and (b)
the need for correct classification of project expenditures and
follow up action on balances remaining from completed projects.
Seven recommendations were provided and were approved by the
Secretary General.
Audit (SG/OIG/AUDIT-02/00) was
undertaken primarily for following up action and to review the
progress made in implementing recommendations of the prior audit of
the NT-based servers (SG/OIG/AUDIT- 08/99). Our examination included
review of systems security and operations, including the security of
the SICE domain and NT servers as well as the functions and
performance of the newly appointed Information Security Officer
(ISO). The audit determined that overall progress has been made
within OAS Information Systems with regard to NT domains and Oracle
Server security and operational control. Physical security is much
better, many technical exposures have been closed, an internal
reorganization has provided administrative responsibilities and the
appointment of the ISO has increased security focus. Although the
Secretariat for Management is in agreement with the findings and
recommendations of the report, there are a number of challenges,
which face the OAS Information System and should be effectively
addressed. One concern is that although some progress had been made,
many of the original findings and recommendations of the previous
audit, which had been declared, completed by OAS staff were still
incomplete. At the time of the audit, the auditor concluded that 20
of the original 44 findings were completed and closed and 24 were
incomplete and still outstanding. We were told that funds requested
in the 2001 budget for implementing critical recommendations for
systems upgrades, increased systems security and additional human
resources were not approved. The nine high risk recommendations (to
be implemented in 30 days) and four medium risk recommendations (to
be implemented in 90 days) which were provided to address the
findings of this audit have been approved by the Secretary General.
The OIG continues to monitor efforts made by the Secretariat for
Management in addressing audit findings and the Inspector General is
satisfied that every effort is being made by the Secretariat to
comply with the recommendations within the constraints of available
resources.
Audit (SG/OIG/AUDIT-03/00) was
undertaken to review progress made in implementing recommendations
of the prior audit of Oracle Government Financials™ (SG/OIG/AUDIT-09/99)
and the new Oracle Human Resources family of applications which went
into production this year. Because the same hardware/system software
and technical support organizations are similar for both families of
applications and because high-risk recommendations have not been
implemented, weaknesses identified in the previous audits also
affect Human Resources. The auditor determined that of the 20
approved recommendations in the 1999 audit, only two might be said
to be completed. The lack of completion of the work to solve the
problems identified in the prior audit causes the OIG serious
concern, particularly because recommendations for standards of
auditability were not implemented. Additionally, there were no
responsibilities established for the auditors to effectively trace
activities within the Oracle Financials™ or Project Accounting.
Because the requested access to the system was not given, the
technical auditor had to use a more difficult means of extracting
the technical evidence.
The data control issues addressed in
the audit report are extremely serious and should be addressed as a
priority, particularly since the auditor found that the financial
data in the Oracle Financials™ System did not always represent the
financial status of certain programs, projects, offices or
organizations. The audit also identified a need for formally
documented organization wide security policies and procedures and we
are pleased to report that this is now in process. However, there is
an urgent need for written policies and procedures for the
operational processes resulting from the Oracle Financials™
System. The audit also determined that control over significant
aspects of the Oracle Financials™ and payroll applications and
related systems and hardware is not adequate and needs improvement.
In the 1999 audit report, the Board of External Auditors stated that
weaknesses in control structure identified by the OIG were not
immediately addressed and these impacted on the 1999 financial
operations. They also added that because ongoing problems are
significant, OAS management must continue to take appropriate action
to ensure adequate and reasonable controls over the financial
resources. Nine high-risk recommendations and five medium risk
recommendations were approved by the Secretary General. We wish to
point out that the recommendations outlined in this audit report had
originally been provided in the prior audit report.
Management's commitment to competence
is an important factor in ensuring a positive control environment.
The audit report states that the Assistant Secretary for Management
must ensure that appropriate arrangements are made for more
effective overall management of the Oracle Technical Environment,
ensure those critical business processes that are conducted are
properly documented and determine appropriate financial and staffing
requirements for an environment that sets a positive and supportive
attitude toward internal controls.
We are pleased to report that work
has now started on the recommendations and we commend the
Secretariat for Management for the significant progress, which has
been made. Training classes have been offered to some departments
specifically to meet their needs. Discussions to address the
apparent overlapping of responsibilities between the Department of
Technology and Facility Services (DTFS) and the Department of
Management Analysis, Planning and Support Services ( MAPSS) and the
Department of Financial Services (DFS) are ongoing and this matter
should soon be resolved. Subsequent to the issue of the audit
report, MAPSS designed a series of systematic detailed Oracle
training courses to provide users, including GS/OAS Executives, the
necessary knowledge for performing assigned responsibilities. The
Memorandum dated July 27, 2000 from the Assistant Secretary for
Management to all Executive and Assistant Secretaries, Directors and
Office Chiefs provided an outline of some of the attributes of the
Oracle Financials™ and proposes a plan of "hands on"
training and evaluation for all staff members to ensure that all
staff members possess the required skills for performing their
assigned responsibilities. That memorandum, which was issued in
response to specific audit recommendations, is designed to improve
overall system security and awareness, provide staff with ability to
manage their financial information within the Oracle System and
retrieve required financial information from the system for
reporting purposes.
Audit SG/OIG/Audit 04/00 was undertaken to evaluate the
administrative and internal controls of Petty Cash funds at
Headquarters and ensure compliance with the OAS directives and
procedures. Our examination determined that all Petty cash accounts
were accounted for and all expenses were supported by documentation.
However, we found that the Department of Financial Services (DFS)
and Petty Cash Custodians do not always comply with OAS procedures
regarding the maintenance and disbursement of Petty Cash Funds. The
main weaknesses identified were:
- The listing provided by DFS was
incomplete as it omitted one custodian.
- Petty Cash funds, although not
large amount, were inappropriately deposited in personal
OAS/Credit Union accounts of two custodians.
- Six of the 15 custodians did not
have prior authorization before disbursing funds and some did
not complete the required OAS Form 370 before making
disbursements.
- In some cases certain custodians
both disbursed and approved the transaction and some custodians
did not maintain on file the required specimen signature of the
individual authorized to disburse these funds.
- Although no transactions were
processed since 1998 one custodian retained the vouchers and did
not submit these to the DFS for retirement of the account.
Four recommendations were provided
for improved internal controls and have been approved by the
Secretary General.
Audit (SG/OIG/AUDIT-05/00) was
performed to identify those controls in effect over the operational
activities of the GS/OAS Office in Saint Kitts and Nevis (OAS St.
Kitts and Nevis). We examined selected operational and financial
activities including cash receipts and disbursements for the period
January to December 1999. We evaluated effectiveness, efficiency and
economy of internal controls to determine whether the office is
executing its responsibilities in accordance with OAS rules and
procedures. We ascertained that, for the most part, internal
controls in the GS/OAS in Saint Kitts and Nevis are adequate for
providing proper authorization and recording of transactions,
activities and disbursements and adequate safeguards over assets.
The main weaknesses identified during the audit were the need for
that office to (1) comply with OAS directives regarding personal use
of the telephone (2) maintain a mileage log for the official vehicle
(3) ensure that monthly Attendance Reports submitted to the
Department of Financial Services are accurate and (4) provide the
annual inventory listing for proper recording of OAS assets. The
Director of the GS/OAS Office in Saint Kitts and Nevis reimbursed
the OAS for his personal telephone calls, which were identified
during the audit. We also found that the Department of Financial
Services (DFS) did not maintain a record of authorized signatures
for all local bank accounts in the Member States as required by OAS
guidelines. We reviewed two projects executed in the GS/OAS Office
in Saint Kitts and Nevis during the audit period (1) Small Business
Development and (2) Computer Programming and Entrepreneurial
Training. The audit determined that project balances in the Oracle
Financials™ System at Headquarters did not agree with the
disbursement registers in the National Office because amounts were
erroneously posted to the wrong projects and there were clerical
errors in the disbursement register. More effective management of
projects by project managers at Headquarters is needed to ensure
that disbursements are properly recorded and account balances are
accurate. Thirteen recommendations were provided and approved by the
Secretary General.
Audit (SG/OIG/AUDIT-06/00) was
performed to identify those controls in effect over the operational
activities of the General Secretariat Office in Antigua and Barbuda
(OAS Antigua and Barbuda). We examined selected operational and
financial activities including cash receipts and disbursements for
the period January to December 1999 to evaluate effectiveness,
efficiency and economy of internal controls and to verify whether
the office is executing its responsibilities in accordance with OAS
Rules and Procedures. We ascertained that for the most part, the
GS/OAS Office in Antigua and Barbuda records all operational
transactions. The main weaknesses identified during the audit were
the need for that office to (1) comply with OAS directives regarding
personal use of the telephone (2) maintain a mileage log for the
official vehicle (3) ensure that attendance reports submitted to the
Department of Financial Services are accurate (4) submit quarterly
reports on goods imported duty free in that Member State and (5)
provide the annual inventory listing for proper recording of OAS
assets. The Director of GS/OAS Antigua and Barbuda reimbursed the
OAS for his personal telephone calls, which were identified during
the audit. The audit also identified a need for training in OAS
operational directives for the Secretary/Technician, which was
provided by the GS/OAS Office in Saint Kitts and Nevis prior to the
completion of the audit report. Our earlier comments regarding the
need for the Department of Financial Services to maintain a record
of authorized signatures for all local bank accounts in the Member
States as required by OAS guidelines are also relevant for the
GS/OAS Office in Antigua and Barbuda. Two projects were executed in
Antigua and Barbuda during the audit period: (1) The Promotion of
Environmentally Sustainable Agricultural Pest Management Systems
through the Use of Biopesticides such as Neem and (2) the Integrated
Approach to Development Planning and Land Management for
Environmental Sustainability. We were unable to review these
projects because (1) project records are retained by the Executing
Agency in another Member State and (2) the disbursement period was
extended due to delays in carrying out project activities because of
hurricane damages. The audit also identified an unpaid liability for
automobile expenses related to the Parham Harbor Project, which was
completed in 1997. Twelve recommendations were provided for approval
of the Secretary General.
Staffing
During the period ended June 30, 2000
the recruitment of auditors to fill the four vacant positions in the
OIG was in process. As a result of this process three auditor
positions were filled with significantly experienced and qualified
auditors. Recruitment for the position of Deputy Inspector
General--the only remaining vacant position in the OIG--is in its
final stages and it is expected that the position will shortly be
filled.
Other
The OIG continued to
participate as observers in meetings particularly related to the
Selection and Bids Committee and the Oracle Financials™ System.
Linda
P. Fealing
Inspector General
August 14, 2000
July
1 to December 31, 2001
Audit
Reports
Thirteen audits were performed during
the period July 1 through December 31, 2000 and recommendations were
provided to correct identified internal control weaknesses. All
audit reports were approved by the Secretary General.
Audit SG/OIG-07/00 was performed with
focus on the new policies and procedures of the procurement process,
which are outlined in Executive Order 00-1 Corr.1. The audit
reviewed selected samples of the integrated functions related to the
procurement process including the requisition, purchase, payment and
posting of procurement transactions during 1999 and 2000. The
implementation of the Oracle Financialsä System has changed OAS
procurement processes. The new system now requires originating
departments to forward a requisition to the Office of Procurement
Management Services (OPMS) for preparation and approval of a
purchase order. The audit determined that the System works to a
certain degree but not to its full function in terms of data
accuracy, consistency, data integrity, degree of automation and user
friendliness. Subsequent to the issue of the draft report, we were
informed that several of the weaknesses identified in the audit
regarding negative encumbrances, reconciliation of invoices, open
purchase orders, zero balances and reconciliation of the purchase
order file to the encumbrances recorded in the General Ledger, were
corrected. We commend the General Secretariat for Management for
those efforts undertaken to effectively manage and control the
procurement process and correct the weaknesses identified in the
audit. We encourage continued OPMS monitoring of the integrated
processes of OAS procurement to ensure the adequacy of internal
controls.
Audit SG/OIG-08/00 was undertaken to
evaluate internal controls in the GS/OAS Office in Guatemala. The
audit determined that there is need for more effective supervision
by the Director of that office, as well as compliance with OAS
directives relating to the disbursement functions, bank
reconciliations, record of authorized signatures in local bank
records and record of OAS assets maintained by the Department of
Technology and Facility Services (DTFS). We reviewed four projects
executed in that Member State: (1) Assistance to the Supreme
Electoral Tribunal in Guatemala (2) Diminishing Abstinence in
Guatemala, (3) 1999 Electoral Observatory Mission and (4)
Modification of Schools Curriculum. The audit determined that those
projects were executed in accordance with their respective
agreements and that project objectives were achieved.
Audit SG/OIG-09/00 provides the
details of our review of the Culture of Dialogue (PROPAZ) and the
Assistance for Demining projects, which were also executed in
Guatemala. The audit determined that the projects were successfully
executed in accordance with the respective agreements.
The main purpose of Audit SG/OIG-10/00
was to review the internal controls relating to selected GS/OAS
payroll processes, following the implementation of the new Human
Resources/Payroll Module. We determined that despite the limited
time available for preparation, the system was successfully
implemented. The ability to process salaries on time, with minimum
glitches during the developing, transition and implementation
periods was primarily due to the hard work, commitment and
dedication of the staff. The main weaknesses identified were (1)
policies and procedures are not yet documented for ensuring
consistency in the application of payroll processes (2) journal
entries used to record transactions are not always documented (3)
there was a lack of an adequate audit trail through which
transactions, which have been processed such as reimbursements for
salary overpayments, may be reviewed (4) despite the recommendations
of a 1999 audit report, all claims for overtime were not supported
by the appropriate security records to document claimants' presence
at OAS during the hours paid, (5) all Notifications of Personnel
Action (NPAs) were not prepared on a timely basis and were not
effectively reviewed by DFS and (6) GS/OAS did not comply with the
Staff Rules regarding special duty allowances for employees who have
been assigned duties of a higher level.
Audit SG/OIG-11/00 was performed to
identify internal controls of the operational activities of the
General Secretariat Office in Peru (OAS Peru). The audit determined
that internal controls were less than satisfactory in the
operational processes of that office, including receipt and
disbursement of OAS funds, preparation of bank reconciliations and
quarterly releases for goods imported duty free. There was an
apparent lack of the necessary understanding of OAS financial rules
and regulations by the Administrative Technician/Secretary of OAS
Peru and the Director of that office did not provide effective
supervision. The three projects reviewed during that audit were: (1)
the Field Research Site Tarapoto (2) Electoral Observatory Mission
and (3) the Sustainable Development of the Amazon Frontal areas. The
OIG determined that although project objectives were achieved,
progress and final reports were not provided to donors on a timely
basis and there is a need for more effective project management from
Headquarters.
Audit SG/OIG-12/00 reviewed the
project for Joint Reconstruction of Homes in Communities of Central
and Northern Nicaragua and determined that project objectives were
achieved. However, there is need for (1) more effective management
supervision from Headquarters, (2) for strengthening internal
controls in administrative functions and (3) compliance with OAS
financial directives in the receipt and disbursement of project
funds.
The main objective of Audit SG/OIG-13/00
was to determine whether the Inter-American Telecommunication
Commission (CITEL) fulfills its mandate and to evaluate its
administrative and internal controls in keeping with assigned
responsibilities. We ascertained with reasonable assurance that
internal controls in CITEL are adequate, that CITEL complies with
GS/OAS directives for proper authorization and disbursement of
expenditures. The main weaknesses identified were the need to: (1)
update some job descriptions to record duties actually being
performed by some individuals (2) ensure that monthly leave reports
and leave balances are correct and (3) notify the Department of
Technology and Facility Services (TFS) of surplus/ obsolete items
for the timely update of the records related to fixed assets.
Audit SG/OIG-14/00 reviewed the
internal controls for financial transactions of the new
Inter-American Agency for Cooperation and Development (IACD) i.e.,
receipt and disbursement of funds. The audit also set out to
determine whether the computer system used by the IACD for financial
transactions is operating in an effective and efficient manner and
satisfies financial reporting requirements. IACD policies and
procedures are not yet available and consequently, the Agency is
required to follow the existing guidelines and procedures of the
General Secretariat. The audit revealed several inefficiencies of
the computer system as well as the need for monthly reconciliation
of expenditures by the IACD against account analysis reports, which
are produced by the Oracle Financials™ System. Further, there is
need for procedural manuals, more effective supervision and
improvement in the financial operational processes, as well as
compliance with GS/OAS procedures, including Staff Rules.
Recommendations were provided for an effective review of the
efficiency and effectiveness of the computerized financial system
that is currently being used by Inter-American Agency for
Cooperation and Development to ensure that an efficient system is
available for IACD accounting and reporting purposes. Other
recommendations were also provided to correct internal control
weaknesses which were identified.
Audit SG/OIG-15/00 was undertaken as
a follow up to the 1999 audit of the Department of Financial
Services (DFS) and to evaluate the administrative and internal
controls of the following operational processes: (1) Cash Receipts
and Receivables, Payables and Disbursements (3) Petty Cash, Bank
Accounts and (4) Bank Reconciliations. The implementation of the
Oracle Financials™ System has significantly changed some DFS
operational processes. Despite those weaknesses identified, the
audit determined that there is marked improvement in internal
controls for those DFS operational processes, which were examined.
It is the opinion of the OIG that the December 2000 bank
reconciliation process shows marked improvement, mainly because of
the absence of a large number of adjusting entries for stale dated
checks and other accompanying schedules.
The audit determined that there is
need for clear audit trails to facilitate the review process and
document all adjusting entries, so as to ensure transparency in the
recording and accounting functions related to the financial data and
information contained in the Oracle Financials™ System. Despite
the prior audit of Petty Cash Funds at Headquarters (SG/OIG-04/00),
a list of Petty Cash Custodians at Headquarters was not up to date
and Petty cash balances in the GS/OAS Offices in the Member States
could not be confirmed, as the listing of the authorized persons and
relevant amounts was not available. Other weaknesses identified were
(1) journal entries used to record transactions and make changes to
initial recorded entries are not documented on the supporting
documents, (2) DFS did not maintain copies of the signature cards
with authorized signatures for the local banks in the Member States
where GS/OAS offices are located (3) DFS was not following its
"stop payment" policy for checks that had not been
presented to the bank within 180 days of issuance and (4) bank
reconciliations were not prepared on a timely basis. At the time of
the audit, desk procedural manuals to document DFS operational
processes were not yet available. However, these have now been
finalized and distributed.
Audits SG/OIG-16/00 and SG/OIG-17/00
were performed to identify controls in the General Secretariat
Offices in Dominica and Barbados. We examined selected operational
and financial activities including cash receipts and disbursements
for the period January 1999 to August 31, 2000. We evaluated
effectiveness, efficiency and economy of internal controls to
determine whether those offices are executing their responsibilities
in accordance with OAS rules and procedures. The audit determined
that the GS/OAS Offices in Dominica and Barbados are effectively
managed and that strong internal controls exist for safeguarding OAS
assets, proper recording of transactions and amounts, efficient use
of resources and compliance with established rules and directives.
We also reviewed the ongoing Youth Technology Resource Centers and
Mini-Orchid Tissue Culture/Biotechnology projects executed in those
Member States. The audit found no discrepancies in the disbursement
records and determined that project objectives have been achieved.
Main weaknesses identified were the need to: (1) comply with OAS
directives regarding two signatures for checks in excess of
US$5,000, (2) maintain a postage log. (3) submit quarterly reports
on releases of goods imported duty free and (4) update records at
Headquarters for OAS fixed assets.
Audit SG/OIG-18/00 reviewed the
Multinational Integrated Approach to Development Planning and Land
Management for Environment Sustainability Project, which was
executed in three Member States. The main weaknesses identified were
(1) funds were disbursed by the Executing Agency after the December
31, 1999 deadline, contrary to the project agreement (2) the total
value of the project equipment listed on the inventory listing
provided by the Executing Agency did not agree with the cost of
equipment purchases reported in final reports or the supporting
vouchers (3) all disbursements were not supported by adequate
documentation and (4) there is need to reimburse the FEMCIDI account
for the balance of unused project funds.
Audit SG/OIG-19/00 reviewed the
operational activities of the OAS Model General Assembly Program (MOAS)
for 1999 and 2000. The program is designed to enable high school and
university students develop knowledge and skills of participatory
democracy through the experience of representing a member nation at
a MOAS. OAS topics have been incorporated into the formal curricula
of several hemispheric academic institutions, some participating
universities have created OAS depository libraries containing OAS
documents and since 1994, MOAS pilot programs have been held in some
Member States. In 1996, a Cooperative Agreement was signed between
the GS/OAS and the MOAS Inter-American Foundation, which was created
to promote, assist and support the MOAS. In 2000 a third Model
Assembly, called MAYA MOAS was started. Interest and participation
in the MOAS have increased substantially since its inception and
throughout the years, the main objectives of the Program have been
achieved. The audit determined that the major part of this growth
can be traced to the present Coordinator, whose missionary zeal,
dedication, knowledge and love for its objectives are exemplary.
However, there is an urgent need to establish the base for
performing specific procedures to handle all the activities of the
Program, including the selection of locations for the MOAS, the
establishment of a fee structure and exemptions from payment. In
order to ensure its continued success, the MOAS program requires
additional resources, including training in the Oracle Financials™
System for the GS/OAS staff members of that program, adequate
facilities, and a competent back up for the Coordinator. In
addition, there is need for (1) improvement in the management of the
administrative activities of the MOAS, (2) the strengthening of
internal controls regarding financial transactions, including
receipt and timely deposit of funds, (3) proper segregation of
duties in the operational processes, and (4) classification and
allocation of fees and disbursements for improved transparency and
accountability in respect of each MOAS.
Staffing
The position of Deputy Inspector
General was filled by a national of Peru with significant audit
experience. She reported for duty in January 2001.
Other
The staff members of the OIG
continued to participate as observers in selected meetings related
to the operational activities of the General Secretariat.
Linda
P. Fealing
Inspector General
March 2001

|